Cincinnati Habitat Build - 2008-09

Pictures on Week 3

Posted on 23-Nov-09 by Bill Fant

  • Week 3 -Buckets of debris moved to dumpster in Avondale - 5 truck loads - View larger image
  • Week 3 -Removing the Limestone rock from Chimney base - View larger image
  • Week 3 -Removing the Limestone rock from Chimney base - View larger image
  • Week 3 -Sheeting second floor - View larger image
  • Week 3 -Sheeting second floor - View larger image
  • Week 3 -Slowly removing Chimney - One rock at a time. - View larger image
  • Week 3 -Rock by Rock - View larger image
  • Week 3 -Rock by Rock - View larger image
  • Week 3 -Austino knocking chimney loose - View larger image
  • Week 3 -Flooring first floor - View larger image
  • Week 3 -Flooring first floor - View larger image
  • Week 3 -Completed Second Floor - Front room - View larger image
  • Week 3 -Removing Chimney debris from basement in buckets - View larger image
  • Week 3 -All that is left of the chimney is loose debris - View larger image
  • Week 3 -Completed First Floor Front Room - View larger image
  • Week 3 -Reframed flooring where chimney was located - View larger image
  • Week 3 -Completed First Floor Middle Room - View larger image
  • Week 3 -Chimney rubble - View larger image
  • Week 3 -New joists in 1st floor to span opening from chimney - View larger image
  • Week 3 -New joists in 1st floor to span opening from chimney - View larger image
  • Week 3 -Basement - Complete - back room - all plumbing and electrical removed - View larger image
  • Week 3 -Basement - Front room - Almost empty! - View larger image
  • Week 3 -Week three - Front of House - View larger image

 

Pages

Work Schedule for the next 4 weeks

Schedule to Work