Week 0 -Basement Stairs -
View larger image -
Week 0 -West Basement - Chimney to be removed -
View larger image -
Week 0 -West basement behind Chimney -
View larger image -
Week 0 -East Basement -
View larger image -
Week 0 -Basement Stairs - Bottom -
View larger image -
Week 2 -Rear Basement cleanup is complete -
View larger image -
Week 3 -Basement - Complete - back room - all plumbing and electrical removed -
View larger image
-
Week 5 -Basement - front rooms - power washed -
View larger image
-
Week 5 -Basement - rear room - power washed -
View larger image
-
Week 17 -Stairs to nowhere…….Jim I think we may have a problem. -
View larger image
-
Week 17 -Furnace and Ducts -
View larger image
-
Week 18 -New basement Stairs -
View larger image
-
Week 18 -New basement Stairs -
View larger image
-
Week 18 -New basement Stairs -
View larger image
-
Week 20 -A clean and dry basement -
View larger image -
Week 20 -A clean and dry basement -
View larger image -
Week 20 -Chimney cap -
View larger image -
Week 20 -Basement stairs -
View larger image -
Week 21 -Bob's basement floor pole. -
View larger image -
Week 22 -Jim works on the basement header -
View larger image
-
Week 26 -The basement stairs are ready to mud -
View larger image
-
Week 26 -More trim ready for installation next weekend. -
View larger image
-
Week 27 -The electrical panel is in place -
View larger image
-
Week 27 -Basebard trim waiting on a second coat of paint -
View larger image
-
Week 27 -The Basement Staircase -
View larger image
-
Week 29 -Joe leads the cleanout of the basement spaces -
View larger image
-
Week 29 -Bob, Pete and joe are ready to hire out to do glass block windows -
View larger image
-
Week 29 -Most of the junk is out of the basement -
View larger image
-
Week 30 -From the basement - front glass block window -
View larger image
-
Week 30 -From the basement - 2nd glass block window -
View larger image
-
Week 30 -From the basement - 3rd glass block window -
View larger image
-
Week 30 -From the basement - 4th glass block window -
View larger image
-
Week 32 -The new electrical panel is ready for inspection -
View larger image
-
Week 32 -Insulation is above basement walls -
View larger image
-
Week 33 -Final glass block window in basement -
View larger image
-
Week 33 -Final glass block window in basement -
View larger image
-
Week 33 -Basement Stairs - side rails are done -
View larger image
-
Week 33 -Messages to our family -
View larger image
-
Week 33 -Messages to our family -
View larger image
-
Week 33 -Basement Stairs - side rails are done -
View larger image
-
Week 33 -Basement Stairs - side rails are done -
View larger image
-
Week 33 -The laundry tub is installed and working -
View larger image
-
Week 33 -Basement stairs waiting on the handrail -
View larger image
-
Week 33 -The temporary toilet is now gone -
View larger image
-
Week 33 -The basement has lights -
View larger image