Cincinnati Habitat Build - 2008

Views of the Second Floor Front Room by Week

Posted on June 15th by Bill Fant

  • Week 0 -2nd Floor - West Room - Ceiling to be raised - View larger image
  • Week 2 -2nd Floor - Front Room - All Done - View larger image
  • Week 3 -Completed Second Floor - Front room - View larger image
  • Week 8 -Still no roof over front - View larger image
  • Week 9 -Second Floor Front Room - View larger image
  • Week 10 -Who made this mess? - View larger image
  • Week 10 -Front room walls - 2nd floor - View larger image
  • Week 13 -Completed Wall in Front bedroom - View larger image
  • Week 15 -Second Floor looking through front bedrooms - View larger image
  • Week 15 -Second floor hallway looking to front of house - View larger image
  • Week 15 -New window in second floor front bedroom - View larger image
  • Week 16 -Front bedroom - 2nd floor - View larger image
  • Week 16 -Closet at front of second floor - View larger image
  • Week 16 -Front bedroom - 2nd floor - View larger image
  • Week 20 -Second Floor - Front closet - View larger image
  • Week 21 -Thermex insulation in second floor rafters - View larger image
  • Week 22 -Completed Thermex in second floor front bedroom - View larger image
  • Week 22 -Second Floor Thermex Ceiling Insulation - View larger image
  • Week 23 -Completed second floor closet - View larger image
  • Week 23 -Completed second floor front bedroom - View larger image
  • Week 24 -End of Day on Friday - Front Bedroom - second floor ceiling - View larger image
  • Week 24 -End of Day on Friday - Front Bedroom - second floor ceiling - View larger image
  • Week 24 -Second floor hall and front bedroom - View larger image
  • Week 24 -Day 4 - Second Floor Front Bedroom - View larger image
  • Week 24 -Day 4 - Second Floor Front Bedroom - View larger image
  • Week 25 -Aveda applied the first coat of paint - View larger image
  • Week 25 -Aveda applied the first coat of paint - View larger image
  • Week 25 -Aveda applied the first coat of paint - View larger image
  • Week 27 -The last closet - Second floor font bedroom - View larger image
  • Week 28 -Diane …… found the next best hide and seek location - View larger image
  • Week 28 -Where did Dave come from? - View larger image
  • Week 28 -Setting the new window in the attice space - View larger image
  • Week 28 -Front bedroom - second floor - View larger image
  • Week 28 -Joseph's new windows in the attic space - View larger image
  • Week 28 -Our last drywall - Thanks Bob, Pete and crew - View larger image
  • Week 28 -Front bedroom - second floor - View larger image
  • Week 29 -And so is the second floor front bedroom - View larger image
  • Week 30 -The closet doors in the front bedroom are done. - View larger image
  • Week 30 -The second floor front bedroom is done - View larger image
  • Week 31 -The front bedroom closets and trim are all complete - View larger image
  • Week 31 -The attic Space is done - View larger image
  • Week 32 -Second Floor front bedroom - lights, smoke detectors, action - View larger image
  • Week 32 -Second Floor front bedroom - custom doors are finished - View larger image
  • Week 33 -The front bedroom is ready for carpet - View larger image
  • Week 33 -The front bedroom is ready for carpet - View larger image

 

Pages

Work Schedule for the next 4 weeks

Schedule to Work